Summary and key findings
- The report discusses recommendations for enhancing the performance of public investment management in Uganda.
- The current public investment program (PIP) is described as overextended.
- A stock-take of the PIP is required by September 2017 to serve as the basis for further decisions.
- Cabinet endorsement of important decisions on the PIP is needed to provide a framework for subsequent planning, budgeting and decision making by the Ministry of Finance, Planning and Economic Development (MoFPED), the National Planning Authority (NPA), and Ministries, Departments, and Agencies.
- To inform the Cabinet decision on the PIP, a comprehensive review of the PIP should be conducted each September/October jointly between the MoFPED, the NPA and the sectors concerned under the auspices of the Development Committee.
Recommendations and procedural actions
- Conduct a stock-take of the PIP by September 2017.
- Secure Cabinet endorsement of key PIP decisions to provide a clear framework for MoFPED, NPA, and sectoral entities.
- Institutionalize a comprehensive PIP review each September/October, carried out jointly by MoFPED, NPA, and the relevant sectors under the Development Committee.
Scope, subject areas, and keywords
- Subject areas: Budget planning and preparation; Expenditure; Government cash forecasting; Medium-term budget frameworks; Public financial management (PFM); Public investment and public-private partnerships (PPP).
- Keywords: appraisal process; Budget planning and preparation; cash flow; CR; DC guideline; DC Guidelines; DC review; Global; Government cash forecasting; investment project; ISCR; Medium-term budget frameworks; physical asset; PIM processes; PIP review; PPP feasibility study; Public investment and public-private partnerships (PPP).